Student tablet deployment – Seine-Maritime Schools
Multi-site institutional project – 10 schools – 2 consecutive years
Carried out as a subcontractor for a national integrator
Les points clés
Key highlights

10 schools out of 109

1200+ tablets/year

6° students equipped

2024 & 2025

Technical Coordination
Project Background
As part of a departmental digital transformation program for schools, tablets were deployed and assigned to 6th grade students, with the goal of supporting them throughout their middle school years.
This institutional project required a high level of expertise in preparation, reliability, and standardization, with devices needing to be operational from the moment they were handed to students and designed for multi-year use.
Tech-IT was involved for two consecutive years across 10 public schools as a subcontractor for a national integrator (ESN), operating across multiple school sites, requiring on-site coordination, adherence to procedures, and management of constraints specific to the school environment.
Role & responsibilities
Technical deployment coordinator – Multi-school scope
Across 10 schools, Tech-IT served as the on-site technical lead, directly responsible for the smooth execution of deployment operations.
Key responsibilities included:
-
Coordinating technical interventions across multiple school sites
-
Preparing, configuring, and deploying student tablets
-
Quality control of equipment before distribution
-
Strict adherence to deployment and tracking procedures
-
Technical liaison between the integrator, project teams, and schools
-
Managing constraints specific to active school environments
This role required autonomy, operational rigor, and accountability, as the equipment was intended to support students throughout their entire middle school years.
Constraints & environment
-
Institutional project led by a local authority
-
Deployment in active school settings
-
Equipment designed for multi-year use (entire middle school cycle)
-
Multiple sites (10 schools)
-
Strict compliance with ESN schedules, protocols, and procedures
-
High requirements for reliability, reproducibility, and continuity of use